Siding sheds most rain, but some always gets behind it. The water-resistive barrier (housewrap, felt, or taped foam) and flashing catch it and send it back out, as long as every upper layer laps over the one below. Wisconsin's rules: a WRB from top to bottom of every frame wall, housewrap of 5 perms or more, laps of 2 inches horizontal and 6 vertical, flashing at the eight required locations, and no cavity insulation until the wall, windows, and roof are covered.

  • 4 min
  • 5 steps
  • 3 questions
  • Lesson 13 of 111

In this lesson

  1. Why the wall needs a second line
  2. The barrier
  3. Shingle lapping
  4. Where to flash
  5. What to take from this

Why the wall needs a second line

Siding isn’t watertight. Wind drives rain through laps and joints, and water runs behind trim, around windows, and down from decks. The defense is a second drainage plane behind the siding: the water-resistive barrier (WRB), with flashing at every opening and joint, arranged so water that gets behind the siding runs down and back out instead of into the wall.

A two-story townhome under construction, its walls covered in white house wrap printed with a brand name.
A townhome wrapped in house wrap, the water-resistive barrier that sheds water while letting the wall dry. Credit: AG20044018 · CC BY-SA 4.0 · Source

The barrier

Wisconsin requires a WRB on every wood- or metal-frame exterior wall, from the highest point to the bottom of the siding 1. Acceptable materials include polymeric housewraps, spray-applied barriers, #15 asphalt felt, and extruded foam sheathing with permanently taped joints 1. Housewraps must have a vapor permeability of at least 5 perms, so moisture inside the wall can still dry outward 1. Spray-applied WRBs may not be compatible with foam insulation, so check before mixing them 1.

Sequence matters: cavity insulation may not go in until the wall has a water-resistant covering and the windows, doors, and at least roof underlayment are installed 1.

A wall covered with housewrap in courses lapped at least 2 inches, upper over lower, with vertical seams lapped 6 inches; a window with head flashing tucked under the wrap above and a sill pan below; arrows showing water running down and shed outward; and a list of the eight places Wisconsin requires flashing.
Every upper layer laps over the one below it. Credit: StudyCorner diagram after Wis. Admin. Code SPS 321.24 · CC BY 4.0 · Source

Quick check

When may you install cavity insulation in an exterior wall under the UDC?

Shingle lapping

Every layer of the drainage plane follows the rule roof shingles follow: upper over lower. For sheet WRBs 1:

  • Horizontal seams: the upper layer laps over the lower at least 2 inches. Start at the bottom.
  • Vertical seams: lapped at least 6 inches.
  • Rips and tears: patched with the same laps.
  • Penetrations: fastener holes need no sealing; small penetrations (5 square inches or less) get caulked; larger ones get flashed.

A reverse lap, where a lower piece sits over an upper one, catches water and funnels it into the wall. It’s the most common mistake, often made when someone tucks housewrap behind a window flange at the head instead of over it at the sill.

Quick check

You’re wrapping a wall. Which course goes on first?

Where to flash

Corrosion-resistant flashing has to extend to the face of the siding and keep water from re-entering. Joints in flashing are lapped 6 inches if vertical and 2 inches if horizontal, and sealed with compatible exterior-grade sealant 1. Wisconsin requires flashing at 1:

  1. The top of every exterior door and window, unless the window is self-flashing with at least an inch of flange all around.
  2. Where chimneys and masonry meet frame walls.
  3. Under and at the ends of copings and sills.
  4. Continuously above projecting wood trim.
  5. Where porches, decks, or stairs attach to the wall or floor framing.
  6. At wall and roof intersections.
  7. At built-in gutters.
  8. Along the bottom of door openings above grade, which also prepares for a future deck.

Two roof-wall details get specific rules: at a dormer, the rake-wall flashing runs at least half an inch down past the head-wall flashing, and where an eave meets a sidewall, the flashing’s end must kick water away from the wall and onto the roof or into the gutter, the “kickout” that prevents the rotted wall below so many roof-wall corners 1.

The deck ledger is the classic failure: a deck bolted to the rim joist without flashing over it rots the rim from the outside in.

Installing High Tech House Wrap | This Old House Installing housewrap. Credit: This Old House · YouTube standard license · 3:05 · Source

Playback is optional. If the player is unavailable, open the video at its source.

Quick check

Where does the head flashing over a window go relative to the housewrap?

What to take from this

Behind every siding is a drainage plane: a WRB (housewrap of 5 perms or more, felt, or taped foam) from the top of the wall to the bottom, lapped upper over lower, 2 inches horizontal and 6 vertical, with flashing at windows and doors, masonry, sills, trim, decks, roof-wall intersections, gutters, and elevated doors. Kick out water where roofs meet walls, flash deck ledgers, and don’t insulate until the wall, openings, and roof are covered.

Lesson complete

Nice work.

1day streak
0/1today's goal
–correct

Up next · 4 min

Windows and Doors

Next lesson
Sources for this lesson
  1. 1
    Wis. Admin. Code ch. SPS 321, Uniform Dwelling Code: Construction Standards. Wisconsin Department of Safety and Professional Services. verifiedDesign loads (SPS 321.02): complete load path to the foundation; live loads 40 psf floors, 50 garage floors, 40 decks and porches, 20 ceilings with storage, 5 without; roof snow loads from the zone map, Zone 1 (north) 40 psf and Zone 2 (south) 30 psf; wind 20 psf horizontal and uplift or ASCE 7-05; span tables in SPS 325 Appendix A. Frost (321.16): footings and foundations, including stoops and landings, below frost penetration or at least 48 inches below grade, whichever is deeper, never on frozen material; exceptions for ASCE 32 frost-protected shallow foundations, areaways, and clean bedrock. Exits (321.03): two first-floor exit doors separated by the greater of 20 feet or a third of the floor's longest diagonal; egress windows at least 20 by 24 inches net clear opening, sill no more than 60 inches above the floor (a platform if over 46); basement sleeping rooms need a second exit. Ceilings at least 7 feet (321.06). Smoke alarms (321.09) in each sleeping room, outside sleeping areas within 21 feet, and on every level, hardwired and interconnected with battery backup.